126 The ESI-Manager user interface
Manual Energy Storage Inverter ESI-S
7.9.3.5 Setting up the inverter rating parameter
For entering the rating parameter, go to
[/Welcome/Settings/Commissioning/Derating]
The permissible ambient conditions for ESI operation are laid out in
. If the
inverter is installed at locations higher than 1000 m (3300 ft) above sea level, the
maximum inverter output current must be derated by 1% every additional 100m (330ft).