3.2 Unpacking
3.2.1 Pre-installation procedure
Introduction
This section is intended for use when unpacking and installing the robot for the
first time. It also contains information useful during later re-installation of the robot.
Prerequisites for installation personnel
Installation personnel working with an ABB product must:
•
Be trained by ABB and have the required knowledge of mechanical and
electrical installation/maintenance/repair work.
•
Conform to all national and local codes.
Checking the pre-requisites for installation
Action
Make a visual inspection of the packaging and make sure that nothing is damaged.
1
Remove the packaging.
2
Check for any visible transport damage.
Note
Stop unpacking and contact ABB if transport damages are found.
3
Clean the unit with a lint-free cloth, if necessary.
4
Make sure that the lifting accessory used (if required) is suitable to handle the weight
of the robot as specified in:
5
If the robot is not installed directly, it must be stored as described in:
6
Make sure that the expected operating environment of the robot conforms to the
specifications as described in:
Operating conditions, robot on page 38
7
Before taking the robot to its installation site, make sure that the site conforms to:
•
Loads on foundation, robot on page 36
•
Protection classes, robot on page 39
•
Requirements, foundation on page 38
8
Before moving the robot, please observe the stability of the robot:
9
When these prerequisites are met, the robot can be taken to its installation site as
described in section:
On-site installation on page 58
10
Install required equipment, if any.
11
52
Product manual - CRB 1300
3HAC083111-001 Revision: B
© Copyright 2022-2023 ABB. All rights reserved.
3 Installation and commissioning
3.2.1 Pre-installation procedure
Summary of Contents for CRB 1300
Page 1: ...ROBOTICS Product manual CRB 1300 ...
Page 50: ...This page is intentionally left blank ...
Page 662: ...This page is intentionally left blank ...
Page 690: ...This page is intentionally left blank ...
Page 704: ...This page is intentionally left blank ...
Page 720: ...This page is intentionally left blank ...
Page 725: ......