Page 59
© Copyright 2021 ABB. All rights reserved.
Figure 5
-
18: Ringer Load Cable and Routing
Battery Strings Installation
Up to four battery strings can be connected to the CPS6000 Distribution Module.
Warning:
Batteries contain hazardous electrical energy, sulfuric acid, and explosive hydrogen gas.
Follow all precautions noted in the manufacturer
’
s literature accompanying the batteries.
Warning:
If a battery disconnect switch is being used, mount the switch before proceeding and make
sure it is in the OFF/OPEN position prior to making any connections.
Connect Battery Strings
This procedure is used to connect up to four battery strings to the CPS6000.
Step
Action
1.
If battery circuit breakers are required, remove the straps installed by the factory and install the
bullet
-
style circuit breakers into the bottom two positions in the Distribution Module. See Figure 5
-
19.
Caution
: Turn the circuit breakers to the OFF position until the unit is ready to be energized.
2.
Place batteries on the battery trays in a 48 V string arrangement per manufacturer
’
s instructions.
3.
Make battery string V
-
and RTN connections to the Distribution Module. Refer to the appropriate Figures
5
-
19b through 5
-
19e for battery string connections to Distribution Modules.
5.
Secure the cables to the battery terminals with M6 nuts. Torque to 65 in
-
lb (7.3 Nm).
Route Ringer Load Cable through
upper or lower notches in Ringer
and Distribution Module Chassis
Ringer Chassis
Ringer Load Cable
Distribution Module
Ringer Load Cable
Connector
Ring (Black)
Tip (Brown)
EGND
-
Chassis (Bare)
Summary of Contents for CPS6000
Page 6: ...Page 6 Copyright 2021 ABB All rights reserved This page intentionally left blank Jl ll ll ...
Page 36: ...Page 36 Copyright 2021 ABB All rights reserved This page intentionally left blank Jl ll ll ...
Page 82: ...Page 82 Copyright 2021 ABB All rights reserved This page intentionally left blank Jl ll ll ...
Page 98: ...Page 98 Copyright 2021 ABB All rights reserved This page intentionally left blank Jl ll ll ...
Page 124: ...Page 124 Copyright 2021 ABB All rights reserved This page intentionally left blank ...
Page 146: ...Page 146 Copyright 2021 ABB All rights reserved This page intentionally left blank ...
Page 152: ...Page 152 Copyright 2021 ABB All rights reserved This page intentionally left blank ...
Page 174: ...Page 174 Copyright 2021 ABB All rights reserved This page intentionally left blank ...
Page 188: ...Page 188 Copyright 2021 ABB All rights reserved This page intentionally left blank ...
Page 192: ...Page 192 Copyright 2021 ABB All rights reserved This page intentionally left blank ...
Page 196: ...Page 196 Copyright 2021 ABB All rights reserved This page intentionally left blank ...
Page 198: ...Page 198 Copyright 2021 ABB All rights reserved This page intentionally left blank ...