Installation
34
Connecting CSU
cable
Follow this steps to connect CSU cable to the Arc Monitor:
Warning!
Make sure that supply voltage is switched off!
Follow this steps to connect CSU cable:
1. Remove the protection plug.
2. Connect current sensing cable to lower side right side of Arc Monitor by
pressing.
Current sensing units (CSU) inputs are X1: 21, 22.
Current sensing units (CSU) outputs are X1
:
23.
Note!
Before the system is ready to use, a DIP switch configurations are needed.
For more information, see the chapter “Configurations” on page - 39.
2
1
Summary of Contents for Arc Guard System TVOC-2
Page 1: ...Arc Guard System TVOC 2 Installation and maintenance guide ...
Page 2: ......
Page 8: ...6 ...
Page 10: ...About Arc Guard System 8 ...
Page 54: ...Installation 52 ...
Page 74: ...Human Machine Interface functions 72 ...
Page 82: ...Technical data 80 ...
Page 89: ......