The Safe torque off function 151
STO function maintenance
After the operation of the circuit is validated at start-up, the STO function shall be
maintained by periodic proof testing as per the following maintenance intervals:
See also
on page
Note:
See also the Recommendation of CNB/M/11.050 (published by the European
co-ordination of Notified Bodies) concerning dual-channel safety-related systems with
electromechanical outputs. The proof test for the function must be performed at the
following intervals, based on the safety integrity requirement:
The STO function of the drive does not contain any electromechanical components.
In addition to proof testing, it is a good practice to check the operation of the function
when other maintenance procedures are carried out on the machinery. Include the
Safe torque off operation test described above in the routine maintenance program of
the machinery that the drive runs.
If any wiring or component change is needed after start up, or the parameters are
restored, follow the
on page
. Record all
maintenance and proof test activities in the machine logbook.
Note
: Use only ABB approved spare parts.
Competency for STO operations
The maintenance and proof test activities of the safety function must be carried out by
a competent person with adequate expertise and knowledge of the safety function as
well as functional safety, as required by IEC 61508-1 clause 6.
Mode of operation
Defined maintenance intervals
High demand
maximum 20 years
Low demand
maximum 2 years
Safety integrity
Defined maintenance intervals
SIL 3 or PL e (cat. 3 or 4)
at least every month
SIL 2 (HFT = 1) or PL d (cat. 3)
at least every 12 months
Summary of Contents for ACS880-M04
Page 1: ...ABB machinery drives Hardware manual ACS880 M04 drive ...
Page 4: ......
Page 12: ...12 Table of contents ...
Page 20: ...20 Safety instructions ...
Page 28: ...28 About the manual ...
Page 38: ...38 Operation principle and hardware description ...
Page 48: ...48 Planning the cabinet installation ...
Page 54: ...54 Mechanical installation ...
Page 72: ...72 Planning the electrical installation ...
Page 98: ...98 Electrical installation ...
Page 102: ...102 Start up ...
Page 108: ...108 Maintenance ...
Page 140: ...140 Technical data ...
Page 158: ...158 Mains chokes ...
Page 164: ...164 EMC filters 7 Attach the terminal blocks to the filter 1 6 5 4 3 ...
Page 166: ...166 EMC filters 6 Attach the terminal blocks to the filter 1 2 3 4 ...
Page 168: ...168 EMC filters ...
Page 182: ...Dimension drawings 182 Frame size R1 H1 H2 W D ...
Page 183: ...Dimension drawings 183 Frame size R2 H2 H1 W D ...
Page 184: ...Dimension drawings 184 Frame size R3 D W H1 H2 ...
Page 185: ...Dimension drawings 185 Frame size R4 W H1 H2 D ...
Page 187: ...187 Dimension drawings EMC filters type JFI x1 JFI A1 ...
Page 188: ...Dimension drawings 188 JFI B1 ...
Page 189: ...189 Dimension drawings EMC filters type JFI 0x ...
Page 191: ...191 Dimension drawings Brake resistors type JBR xx ...
Page 193: ...193 Dimension drawings ...
Page 195: ...www abb com drives www abb com drivespartners 3AXD50000028613 Rev A EN 2016 04 11 Contact us ...