Tasks
Connecting the energy storage to the DC/DC converter
Set parameter
120.12 Run enable 1
to
Off
. This makes sure that the DC/DC converter does not start
automatically or unexpectedly after you connect the energy storage.
Switch the control panel to local control mode.
Make sure that the energy storage voltage is below the drive DC link voltage.
WARNING!
Do not close the energy storage disconnecting device if the DC/DC converter is not connected
or not ready to use.
Close the energy storage disconnecting device (customer or system integrator-installed device).
Close the energy storage protective circuit breaker (customer or system integrator-installed device).
Testing the DC/DC converter operation
Set parameter
120.12 Run enable 1
to
On
.
Set parameter
122.01 User Power ref
to 0 A.
Set current limits to low values, for example,
•
130.119 Minimum current
to -50 A.
•
130.120 Maximum current
to 50 A.
Press the control panel Start key to start the converter. After start, increase slowly the value of para-
meter
122.01 User Power ref
.
Check the following signals:
•
102.01 DC voltage
•
102.02 ES voltage used
•
102.08 Total current
•
102.11 Modulation index %
•
130.101 DDC limit word 1
.
Press the control panel Stop key to stop the converter.
78 Start-up
Summary of Contents for ACS880-1604LC
Page 1: ... ABB INDUSTRIAL DRIVES ACS880 1604LC DC DC converter modules Hardware manual ...
Page 2: ......
Page 4: ......
Page 12: ...12 ...
Page 16: ...16 ...
Page 34: ...34 ...
Page 42: ...Kits for ACS880 1604LC R8i unit in Rittal VX25 cabinets 42 Cabinet construction ...
Page 43: ...Stage 1 Installation of common parts Cabinet construction 43 10 ...
Page 45: ...Stage 3 Module installation parts Cabinet construction 45 10 ...
Page 46: ...Stage 4 DDC and energy storage connection 46 Cabinet construction ...
Page 47: ...Stage 5A DC connection with charging Cabinet construction 47 10 ...
Page 48: ...Stage 5B DC connection without charging 48 Cabinet construction ...
Page 49: ...Stage 6 Cooling components Cabinet construction 49 10 ...
Page 50: ...Stage 7 DDC module and filter installation 50 Cabinet construction ...
Page 51: ...Stage 8 Swing frame and shroud installation Cabinet construction 51 10 ...
Page 58: ...58 ...
Page 72: ...72 ...
Page 124: ...124 ...
Page 138: ...138 ...
Page 148: ...148 ...
Page 150: ...R8i DC DC converter module 150 Dimension drawings ...
Page 151: ...BDCL filter module Dimension drawings 151 ...
Page 152: ...Quick connector 152 Dimension drawings ...
Page 153: ...BCU control unit Dimension drawings 153 ...
Page 154: ...BAMU voltage current measurement unit Dimensions in mm 1 mm 0 0394 in 154 Dimension drawings ...