146 Preventive Maintenance
Bypass unit
Isolation switches for Manual Bypass
Pay special attention to the following:
1. The isolation switches should be easy for operation.
2. Conductive grease like “OKS VP980” is applied on contact surface of isolation
switches, apply more if necessary.
3. No loose connection.
4. Check status lamps on front door by operating isolation switches.
5. Check interlock of isolation switches as the table below.
Note:
•
“X” means the operation cannot be executed.
•
“
√
” means the operation can be executed.
•
Any of switches cannot be operated when the selector is in “Operation” or “OFF”
position.
Contactor for Auto Bypass
Pay special attention to the following:
Summary of Contents for ACS580MV
Page 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Page 4: ......
Page 8: ...8 ...
Page 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Page 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Page 83: ...Standard Commissioning Process 83 ...
Page 96: ...96 Standard Commissioning Process ...
Page 121: ...Option 121 IO signals ...
Page 122: ...122 Option Panel control interface System fault ...
Page 140: ...140 Option ...
Page 148: ...148 Preventive Maintenance ...