144 Preventive Maintenance
Motor insulation resistance
Insulation resistance measurement for motor, please refer to
.
Optical fibers
Visual check
Pay special attention to the following:
1. Cracks in the core or the coating.
2. Minimum bend radius (25 mm).
3. Condition of male and female connectors.
4. Installation across sharp edges.
5. Tightness of cable ties.
Attenuation measurement
1. Prepare the tools for attenuation measurement:
•
Tempo 253B light source (1)
•
Tempo 557B power meter (2)
•
10ZP adapter
Summary of Contents for ACS580MV
Page 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Page 4: ......
Page 8: ...8 ...
Page 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Page 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Page 83: ...Standard Commissioning Process 83 ...
Page 96: ...96 Standard Commissioning Process ...
Page 121: ...Option 121 IO signals ...
Page 122: ...122 Option Panel control interface System fault ...
Page 140: ...140 Option ...
Page 148: ...148 Preventive Maintenance ...