73
ACS2000 AFE 2MVA UM
3BHS355653 ZAB E01 REV. H
—
4.3 Unpacking and inspection
Recommended steps for inspecting the drive after delivery.
1. Remove all packaging material carefully.
2. Check the drive and accompanying equipment
for damages.
3. Compare the complete delivery with the pur-
chase order and the packing list.
4. If parts are missing or damaged, immediately
inform the shipping company and the ABB ser-
vice organization.
It is recommended to photograph the damages
and send the photographs to ABB.
Summary of Contents for ACS2000 AFE 2MVA
Page 8: ...General information on manual and equipment ...
Page 13: ...13 ACS2000 AFE 2MVA UM 3BHS355653 ZAB E01 REV H ...
Page 14: ...Terms abbreviations trademarks ...
Page 19: ...19 ACS2000 AFE 2MVA UM 3BHS355653 ZAB E01 REV H ...
Page 20: ...Important note on main circuit breaker ...
Page 48: ...Chapter 3 Control system 49 Control unit 50 Main components 55 I O interfaces ...
Page 69: ...69 ACS2000 AFE 2MVA UM 3BHS355653 ZAB E01 REV H ...
Page 111: ...111 ACS2000 AFE 2MVA UM 3BHS355653 ZAB E01 REV H ...
Page 118: ...Commissioning check list ...
Page 153: ...153 ACS2000 AFE 2MVA UM 3BHS355653 ZAB E01 REV H ...
Page 180: ......