Routing the cables
General guidelines, IEC
•
Route the motor cable away from other cables. Motor cables of several drives can be
run in parallel installed next to each other.
•
Install the motor cable, input power cable and control cables on separate trays.
•
Avoid long parallel runs of motor cables with other cables in order to decrease
electromagnetic interference caused by the rapid changes in the drive output voltage.
•
Where control cables must cross power cables, make sure they are arranged at an
angle as near to 90 degrees as possible.
•
Do not run extra cables through the drive.
•
Make sure that the cable trays have good electrical bonding to each other and to the
grounding electrodes. Aluminum tray systems can be used to improve local equalizing
of potential.
This figure illustrates the cable routing guidelines with an example drive.
min. 200 mm (8 in)
90°
*min. 500 mm (20 in)
1
2
3
3
2
1
4
min. 300 mm (12 in)
2
4
3
min. 300 mm (12 in)
*
Motor cable
1
Input power cable
2
Control cable
3
Brake resistor or chopper cable (if any)
4
Planning the electrical installation 57
Summary of Contents for ACQ80-04 Series
Page 1: ...ABB DRIVES FOR WATER ACQ80 04 drives 0 75 to 160 kW 1 0 to 215 hp Hardware manual...
Page 2: ......
Page 4: ......
Page 18: ...18...
Page 24: ...24...
Page 38: ...38...
Page 50: ...50...
Page 64: ...64...
Page 98: ...98...
Page 110: ...110...
Page 140: ...Frame R3 IP20 140 Dimension drawings...
Page 146: ...146...
Page 162: ...162...
Page 168: ......