Operation Manual / A130-M.. - A145-M..
7 Periodic maintenance work / 7.1 Foreword to maintenance
© Copyright 2022 ABB. All rights reserved.
HZTL4031_EN
Rev.P
February 2022
7
Periodic maintenance work
7.1
Foreword to maintenance
Maintenance work includes regular visual controls and cleaning operations which are inten-
ded to ensure the trouble-free functioning of the turbocharger.
To allow you to observe the standard service intervals and to maintain a high turbocharger
efficiency, Turbo Systems recommends that the cleaning procedure be carried out during
operation. This allows the thermal load of the engine to be kept low while ensuring max-
imum fuel efficiency.
Maintenance inter-
val
Maintenance work
Operating status
24 … 72 h
1)
Cleaning the compressor during operation
Engine load 50 … 85 %
50 … 200 h
1)
Cleaning the turbine during operation
Engine load 20 … 40 %
(guideline value)
According to rating
plate
2)
Cleaning components mechanically
Engine stopped
Table 13: Maintenance table
[h] = Hours of operation
1)
If the maintenance intervals are incompatible with operation of the engine, contact Turbo
Systems.
2)
Turbo Systems recommends having mechanical cleaning carried out by a Turbo Systems
service station during the service work (see also chapter
Service work according to data on
). Otherwise, only carry out mechanical cleaning if cleaning during opera-
tion is not sufficient to achieve the thermal load and the rating of the engine.