37
3. Attach vent piping to the flue pipe adapter
on the boiler at one end and run through the
sidewall of the unit at the other end. All Vent
pipes and fittings are CPVC. Vent piping
must be pitched at a minimum of 1/4 inch per
foot back to the boiler.
4. Install the vent and air intake piping
through the wall into the sidewall vent base.
Use RTV silicone sealant to seal the air
intake pipe. Mount and secure the sidewall
vent base using stainless steel screws. Seal
all gaps between the pipes and the sidewall.
Seal around the sidewall vent base to the wall
ensuring no air gaps.
5. Assemble vent cap to vent base and
securely attach using stainless steel screws.
Figure 18 - Sidewall Vent Base
Figure 19 - Sidewall Vent Cap
Vertical Direct Boiler Venting
For units with Lochinvar Crest boilers
(feature B4 = K, L, M, or N), the air intake
and vent piping is installed to run vertically
through the roof of the unit.
1. Remove shipping covers from openings in
the roof.
Figure 20 - Roof Air Intake and Vent Piping
Shipping Covers
Use only primer and cement approved
for use with CPVC (ANSI/ASTM
F493).
WARNING
Summary of Contents for LZ Series
Page 2: ......
Page 27: ...27 Figure 6 Concrete Pad Mounting with Dimensions Figure 7 LZ Base ...
Page 36: ...36 Figure 17 Typical Flue Vent Piping ...
Page 83: ...83 ...
Page 84: ...84 ...
Page 95: ...95 Flo Trex Cross Section ...