28
Lifting and Handling
If cables or chains are used to hoist the unit
they must be the same length and care should
be taken to prevent damage to the cabinet.
See Figure 9 for additional information.
Before lifting unit, be sure that all shipping
material has been removed from unit. If the
unit is an evaporative-condensed chiller,
make sure the tank is empty before lifting.
Secure hooks and cables at all lifting points/
lugs provided on the unit.
Hoist unit to a point directly above the curb
or mounting rail. Be sure that the gasket
material has been applied to the curb or
mounting rail.
Carefully lower and align unit with utility
openings. Lower the unit until the unit skirt
fits around the curb. Make sure the unit is
properly seated on the curb and is level.
Do not push, pull or lift the unit from
anything other than its base.
Figure 8 - Lifting Points
Summary of Contents for LZ Series
Page 2: ......
Page 27: ...27 Figure 6 Concrete Pad Mounting with Dimensions Figure 7 LZ Base ...
Page 36: ...36 Figure 17 Typical Flue Vent Piping ...
Page 83: ...83 ...
Page 84: ...84 ...
Page 95: ...95 Flo Trex Cross Section ...