14
•
Slide the side bearing with universal bearing onto the support tube & fasten.
>
fig. 3.9
•
Ensure that the motor square spigot is properly engaged in the universal bearing.
>
fig. 3.10
•
Secure the motor square spigot with the supplied cotter pin.
>
fig. 3.11
•
Attach the cover to the side bearing.
>
fig. 3.12
•
Install awning & release fuses.
4
Awning motor wiring:
•
Connect the awning motor and switch (or timer) to the mains.
•
The electrical connection of the awning motor and control may only be carried out by qualified personnel.
•
If the drive should run in the opposite direction after installation, the motor’s upstream and downstream leads (brown + black) must be turned.
3.9
3.10
3.11
3.12
Adjustment cable ESK
The connection diagram for the ESK can be found on page 10.
The connection diagram of time switches differs from this
circuit diagram! Please refer to the corresponding manual
for the connection diagram.
If the end points are set using the ESK, do not connect the
switch or timer until after the end points have been set
(page 11)!
Awning motor
230 V / 50 Hz
INSTALLATION INSTRUCTIONS
3T-MOTORS Tubular motors
| Installation instructions
Side bearing &
Universal bearing
Support tube
Cotter pin
Side bearing
Cover
Power grid
230 V / 50 Hz
1) white = Programming cable, not assigned
2) black = Departure or ascent
3) brown = Departure or ascent
4) blue = N Neutral conductor
5) green/yellow = PE Protective conductor
1) brown / black = L1 / Phase
2) blue = N Neutral conductor
3) green/yellow = PE Protective conductor
1 (L1)
2 (N)
3 (PE)
2 (Up/Down)
3 (Up/Down)
4 (N)
5 (PE)
1
The white wire is unoccupied and
must be insulated. To do this, push
the enclosed wire end cap onto the
wire end and press it together with
crimping pliers or combination pliers.
Wire end cap