3.7 Installing a Board
The installation procedures of SRPUs, LPUs, and service boards are almost the same.
The following section describes the installation procedure of LPUs.
3.7.1 Installation Preparations
z
Wear the ESD-preventive wrist strap, making sure that it is properly grounded.
z
Loosen the mounting screws on the blank filler panel where the SRPU is to be
installed using a Phillips screwdriver and remove the blank filler panel.
z
Prepare the LPU to be installed.
Note:
z
Put the removed blank filler panel away for future use.
z
The LPUs of the S9500 series are hot-swappable.
3.7.2 Installation Procedure
Follow the procedure below to install an LPU:
1)
Turn the ejector levers on the LPU outward simultaneously with both hands, insert
the LPU straight into the chassis along the guide rails until it stops sliding (that is,
the positioning pins on the ejector levers touch the positioning holes on the
chassis).
2)
Turn the ejector levers towards the front panel to drive the positioning pins into the
positioning holes..